REFERENCE LIST for the year 2008-2012
Customer | Project | Performance time (year) | |
---|---|---|---|
SE NAEC «Energoatom» Ukraine |
Zaporozhia NPP |
Delivery and introduction of programmatic-technical complex of CAS of adjusting of turbine separation (PTС ASR TO) of power unit №6 | 2008 |
Delivery and introduction of programmatic-technical complex of flow of the first contour (PTС TPС) for the increase of safety of power unit №5 | 2009 | ||
Yuzhno- Ukrainian NPP |
Delivery and introduction of programmatic-technical complex of the system of adjusting of turbine (PTС SRT) and PTС of electronic regulator of speed (PTС ERS) of turbogenerator of power unit №1 | 2011 | |
Delivery and introduction of equipment of the checking of mechanical sizes of turbine (SСMVT) of power unit system №1 | 2012 | ||
Rovenskaya NPP |
Delivery and implementation of software and hardware complex system of automatic control of reactor compartment control safety system (PTC USB1 SAR) to improve the safety of unit №3 | 2008 | |
Delivery and implementation of software and hardware automation systems for the automatic control system (ATS) full-scope simulator of the PMT-1000 for the prototype unit № 3 | 2010 | ||
Khmelnickaya NPP |
Delivery and implementation of the equipment software and hardware complex system of automatic control of reactor facilities PTC SAR RO for full-scale simulator | 2011 | |
SPE «DFEC Vostokenergo» Ukraine |
Zuevskaya TPS |
Delivery and implementation of the control system of mechanical quantities of steam turbine SKMVT-300 steam turbine vibration monitoring systems SVT-300 (Units 4) | 2011 |
Energygenerating company «DFEC Dneprenergo» Ukraine |
Zaporozhia ТPS |
Delivery and implementation of software and hardware complex electro-hydraulic system of regulation of the turbine K-325-23, 5 (PTC SRT) and the software and hardware complex control system vibration and thermal and mechanical parameters of the turbine K-325-23, 5 (PTC SKMVT) (units 1) | 2011 |
OC «A business concern Rosenergoatom» Russia |
Kalininskaya NPP |
Delivery and implementation of software and hardware complex control mehvelichin (PTC SKM-1TG, PTC SKM-2TG) turbogenerator units № 1, № 2 | 2011 |
Delivery and implementation of software and hardware complex of the automated control systems of the normal operation of the reactor compartment (PTC SAR SNE RO) units № 1, № 2 | 2012 | ||
Delivery and implementation of executive machines IAT-03M, 04M-IAT, IAT-05M, 06M-IAT, IAT-07M (160 pcs.) For power units № 1, № 2 | 2011-2012 | ||
Balakovskaya NPP |
Delivery and implementation of software and hardware complex of the automated control of turbine section (PTC SAR TO) unit № 1 Balakovo | 2012 | |
Nowy- Voronezh NPP |
Further development and implementation of complex software ASUT-500M during the modernization of the control of normal operation of turbine section (SKU SNE TO) unit № 5 | 2011 | |
Rostov NPP |
The development and implementation of software electrohydraulic control systems (software EGSR) in implementing the discharge pulse (IR) and participate in the testing at unit № 1 | 2010-2011 | |
Company «NUCLEAR POWER CORPORATION OF INDIA LIMITED» Republic India |
NPP «Kaiga-3» NPP «Kaiga-4» NPP «RAPP-4» NPP «RAPP-5» |
Author supporting operation of control systems, control and protection systems - software and hardware complex automated control system of turbine unit K-240-4, 0 (PTC ASUT-240) | 2011-2012 |